PCB Design Quotes: Scope Beats the Hourly Rate
Design is quoted either as a fixed scope or as hours, and the difference matters. A fixed price assumes a frozen requirement; if the schematic is still moving, hours is the honest model. Ask what is included — stack-up, impedance calculation, DFM review, fabrication drawings, or only the layout.
Lead times are industry ranges, not commitments. Any factory's actual date depends on its queue that week, and on what else is already scheduled.
ChinaPCB.org does not quote boards and takes no commission. This page exists so that the enquiry you send to a factory is complete the first time. Send it yourself — see how to send an RFQ.
What this quote is priced on
Five to seven variables move the number on a pcb design quote. They are not equally important, and only the first two are usually discussed.
- Scope boundary. Schematic capture, layout, stack-up, impedance, DFM and fabrication drawings are separate deliverables. Most price arguments are about which side of that line a task sits on.
- Layer count and density. Placement and routing time scales with layer count and pin density, not with board area. A small dense board can take longer than a large sparse one.
- Review cycles. A design quoted with two review cycles and delivered after five is a dispute. Naming the number makes the extra work a change order instead of an argument.
- Constraints and simulation. Impedance calculation, signal integrity and thermal simulation are engineering tasks with their own tools. They are rarely free and rarely included by default.
- Tool and data handover. Source design files in your EDA tool cost more than a set of Gerbers, and they are what lets you change supplier later.
The parameters a factory needs
This is the set that has to be in the enquiry before a pcb design price means anything. The third column is why each one changes the answer, which is also the reason a quote that skips it is not really a quote.
| Parameter | What to state | Why it changes the answer |
|---|---|---|
| Schematic and netlist status | Frozen schematic, draft schematic, or a requirement with no schematic yet | This decides whether the quote is layout-only or full design. It also decides whether a fixed price is even meaningful. |
| Mechanical constraints | Outline, mounting holes, connector positions, height limits and enclosure drawing | Mechanical constraints are fixed points the layout must satisfy. Discovering them late forces a re-placement, not a tweak. |
| Stack-up ownership | Whether the designer defines the stack or the factory does | Whoever owns the stack owns the impedance and the fabrication risk. Splitting it between two parties is how impedance targets get lost. |
| Impedance and SI requirements | Single-ended and differential targets, and whether simulation is required | Impedance calculation is a deliverable, not a setting. Simulation is a separate task with its own cost. |
| Review cycles included | How many review rounds are inside the price, and the rate beyond that | Review rounds are the most common source of scope creep in design work and the easiest thing to leave unwritten. |
| Deliverables list | Gerber, drill, fab drawing, assembly drawing, BOM, pick-and-place, source files | A layout without a fabrication drawing cannot be quoted by a factory. The list is the product. |
| EDA tool and file format | Altium, KiCad, Cadence, Mentor, and whether source files are handed over | Tool choice affects both the rate and whether you can maintain the design without the same supplier. |
| DFM and fabrication review | Whether the designer checks against a named factory capability, and which one | DFM against a generic ruleset is not DFM. The check is only useful against the plant that will build the board. |
| Compliance requirements | EMC, safety spacing, IPC class, and any certification the design must support | Clearance and creepage rules change the layout. Adding them after routing means a partial redo. |
Send with the enquiry
- The schematic and netlist, or the requirement if the schematic is also in scope.
- The mechanical envelope: outline, mounting, connector positions and height limits.
- Impedance and SI targets, and a statement of who owns the stack-up.
- The deliverable list, including whether source files are handed over.
- How many review cycles are included, and the EDA tool you need the output in.
Where it goes wrong
- A quote without fabrication drawings. You receive a layout you cannot send out for fabrication, and the missing item is treated as new work rather than as part of the job.
- Fixed price on a moving schematic. Either the price is padded for changes that may not happen, or the work stops at the first change. Hours is the honest model at that stage.
- DFM checked against generic rules. The board passes the designer checklist and fails the factory minimum. The rework is a re-layout, priced as a new job.
- Source files assumed. Gerbers are a manufacturing output, not a design. Without source files, every future change goes back to the same supplier.
Comparing two pcb design quotes
Two prices are only comparable when the parameters above are held constant. Most of the spread buyers see comes from a difference in one of these, not from a difference in factory efficiency.
- Compare the deliverable list line by line. Two design quotes at different prices are usually different scopes.
- Compare review cycles. An open-ended review commitment is priced into the number or excluded from it, never free.
- Compare who owns the stack-up and the impedance calculation.
- Compare whether source files are handed over. It is the difference between hiring a designer and renting one.
What this page does not tell you
This page gives no hourly or per-pin rates, because they vary by region, tool and seniority, and a number here would mislead more than it informs. What is comparable across suppliers is the scope, and that is what the table above asks you to pin down.
Related
- PCB design: what the service covers in practice
- Reverse engineering: designing from a physical sample
- Capability comparison: how to check a design against a plant
- Rigid quotes: where the fabrication drawing goes
Fee structure and editorial independence are described on the about page. What we can and cannot confirm about a factory is on how we verify.