Turn-Key Assembly Quotes: Who Buys the Parts?
In a turnkey quote the factory buys the parts. That moves price risk onto them, so they either add a sourcing margin or quote against the market price of the day with a validity window. Ask which one you are looking at, because a turnkey price with no validity date is not a commitment.
Lead times are industry ranges, not commitments. Any factory's actual date depends on its queue that week, and on what else is already scheduled.
ChinaPCB.org does not quote boards and takes no commission. This page exists so that the enquiry you send to a factory is complete the first time. Send it yourself — see how to send an RFQ.
What this quote is priced on
Five to seven variables move the number on a turn-key assembly quote. They are not equally important, and only the first two are usually discussed.
- Component cost and its date. The largest line in a turnkey quote is material, and material moves. A quote without a validity window is a snapshot presented as a price.
- Sourcing channel. Authorised distributor, franchised excess, or open market. Each step down is cheaper and carries more counterfeit and authenticity risk.
- Long-lead exposure. Parts with long lead times have to be bought ahead or designed around. The factory either carries that inventory or charges you to hold it.
- Minimum order quantities. Component MOQs frequently exceed your board quantity. The surplus is either billed to you or absorbed into the unit price.
- Sourcing labour. Checking availability, finding alternates, verifying authenticity and managing shortages is real work. It appears as a handling percentage.
- Scrap and attrition. Parts damaged in setup belong to whoever bought them. The rate is small per board and significant per order.
The parameters a factory needs
This is the set that has to be in the enquiry before a turn-key assembly price means anything. The third column is why each one changes the answer, which is also the reason a quote that skips it is not really a quote.
| Parameter | What to state | Why it changes the answer |
|---|---|---|
| Authorised sourcing policy | Authorised distributor mandatory, or open market acceptable per line | This is the largest single determinant of material cost and of authenticity risk. Leaving it open lets the supplier choose the risk. |
| Price validity window | How long the material price must hold, and what happens when it does not | A turnkey price without a validity date is not a price. Most disputes on turnkey orders are about this line. |
| Long-lead parts | Which lines have lead times beyond your build date, and whether to buy ahead | Buy-ahead ties up cash and requires your approval. Without it, the build slips or a substitute appears. |
| Brand and alternate policy | Brands you require, brands you accept, and who approves a substitute | Substitution is where cost is quietly removed. If approval is not defined, it happens without you. |
| Surplus and MOQ ownership | Who owns components left over after the build, and who pays for MOQ surplus | MOQ surplus can be a large share of a small order. It has to be allocated before the order, not after. |
| Scrap allowance | The attrition percentage included, and who pays above it | Setup consumes parts. A quote that assumes zero attrition either pads the price or bills you later. |
| Authenticity evidence | Certificates of conformance, traceability to the distributor, and marking inspection | Counterfeit parts look correct until they fail. Paperwork is the only check you can perform before assembly. |
| Currency and Incoterm | Quoting currency, exchange-rate basis, and the Incoterm for delivery | Material is often bought in US dollars and sold in another currency. The basis is a real cost line, not paperwork. |
Send with the enquiry
- BOM with MPNs, quantity per board and per order, and the brands you will accept.
- Whether authorised distribution is mandatory, line by line if it varies.
- The build date, and which lines you know to be long-lead.
- Your policy on MOQ surplus, substitutions and scrap allowance.
- Required authenticity evidence, and how you will audit it.
Where it goes wrong
- Turnkey built on broker parts. It is the cheapest quote on the table and the one that fails incoming inspection six weeks later, when the schedule has no room left.
- No validity date. Material moves weekly. A price without a date is a number the factory can revise the day you accept it.
- MOQ surplus left unallocated. A reel of 4,000 parts for a build of 40 arrives as a charge you did not approve, or as a hidden uplift in the unit price.
- Substitution approved verbally. A different brand with the same value is not the same part. Without written approval, the difference is discovered at functional test.
Comparing two turn-key assembly quotes
Two prices are only comparable when the parameters above are held constant. Most of the spread buyers see comes from a difference in one of these, not from a difference in factory efficiency.
- Compare the validity dates before the prices. A lower price that expires in a week is not lower.
- Compare the sourcing channel per line. Two turnkey quotes at different prices are usually different channels.
- Compare what happens to MOQ surplus and scrap. Those two lines explain most of the gap that labour cannot.
- Compare the Incoterm. Delivered and ex-works prices differ by more than most negotiations on unit cost.
What this page does not tell you
This page gives no component prices and no handling percentages, because both move with the market and with your BOM. What does not move is the set of questions above, and a supplier who cannot answer them is not quoting turnkey.
Related
- Turn-key assembly: the process and where risk sits
- Assembly quotes: the labour-only baseline
- Box-build quotes: turnkey plus mechanics
- RFQ checklist: BOM fields that prevent requotes