黄石广合精密电路有限公司 · Huangshi · Founded 2019 · Not listed; parent Guanghe Technology on SZSE 001389 and HKEX 01989
A university visit page calls this the largest single PCB plant in the world. The company's own homepage gives 29,500 m2. Both cannot be right.
Suits server, switch and optical-module work that needs 12-layer-plus boards at a 9:1 aspect ratio, backed by a parent listed in Shenzhen and Hong Kong. Not yet a stable home for automotive volume: the plant is being retooled toward AI server boards, so ask which lines stay on your programme.
Identity and record
| Registered name (Chinese) | 黄石广合精密电路有限公司 |
|---|---|
| Founded | 2019 |
| Listed | Not listed; parent Guanghe Technology on SZSE 001389 and HKEX 01989 |
| Headquarters | Huangshi |
| Production sites | Guangzhou · Dongguan · Huangshi · Prachinburi (Thailand) |
| Official website | http://www.delton.com.cn |
| Evidence level | Public sources reviewed |
| Last reviewed | 2026-11-11 |
2019, 2021, and a plant that has already changed its job
The legal entity dates from 2019. Ground was broken on the Huangshi project in April 2020, with RMB 5 billion attached to it and a stated aim of being a demonstration plant for high-end PCB manufacturing. Production started in 2021.
What that plant was built to make is on the record and is not what it makes now. The 2021 positioning was consumer, automotive and industrial boards. In a September 2026 investor-relations record the company says it is converting and upgrading Huangshi lines to expand server capacity, with the plant earmarked as the group’s main domestic base for computing-power server PCB.
Two product strategies, five years apart, one building. A buyer with a 2021-era automotive programme is now sharing a shop floor with AI server work. Ask which lines stay on your process route and get the answer in the quotation, not in a slide.
The superlative has exactly one source
“Currently the largest single PCB plant in the world” appears in a Hubei Normal University report on a faculty visit to the company. It is a sentence written by a careers office summarising what it was told on a tour. No annual report, no prospectus, no exchange filing and no company page repeats it.
The same page supplies the other headline claim: the first full-process dark factory in the province’s PCB industry, with equipment connection rates up more than fivefold and output up 80% on roughly 10% more staff. Both statements come from the same article, which means a reader cannot accept the automation number and reject the superlative without explaining why. They stand or fall together.
Neither is worthless. A careers page reporting what a plant manager said is weak evidence, but it is evidence. Treat the dark-factory claim as a claim about one workshop, and the superlative as marketing that leaked into a university newsletter.
29,500 square metres
The group homepage states a site of 29,500 m². Against four plants and 4,998 staff, that number is either a single building or a decade-old figure, and the page gives no unit context. Whatever it measures, it is not the footprint of the largest single PCB plant on earth.
So the two public numbers contradict each other, and the company has published only the smaller one. This is the ordinary condition of Chinese plant marketing: the website is maintained by whoever answers the phone, the superlative is repeated by whoever writes the visit report, and neither is checked against the other. Do not repeat the superlative in a supplier qualification file. Ask for the land certificate and the covered floor area instead, then measure those against your own capacity model.
Certification scope: use the ESG table, not the site
The 2025 ESG report, filed in Hong Kong in April 2026, lists each system against each plant, and that table is the single most useful document on this company. ISO 9001 covers Guangzhou, Huangshi, Thailand and Dongguan. IATF 16949 covers Guangzhou and Huangshi only. Environmental and safety systems cover all four. QC 080000 covers all four. ISO 50001 is Guangzhou and Huangshi. ISO 14064-1 adds Thailand.
The website page on certificates is the older artefact: it still shows ISO 13485:2003 and ISO 27001:2013, withdrawn revisions, with no plant scope at all. A purchasing reviewer who reads only the site will conclude the company is a decade behind. The ESG table shows the opposite for Huangshi, which carries the automotive system.
Request the certificate PDFs with the site address printed on them. A group-level certificate with four addresses on the scope page is not the same document as a certificate for this postal code.
What the product pages promise
Switch boards at 12 layers and above, a 9:1 aspect ratio, laminate one grade above what a server board uses. Optical modules mostly on HDI, built on very-low-loss material or a hybrid with FR-4. SSD boards as rigid-flex with 3D stacking. AI server switch boards and UBB mainboards with multiple PCIe channels and direct links to SXM or OAM accelerator modules. Intel, AMD and Arm platforms, single through four sockets.
That is a coherent server portfolio, and it explains the retooling. Note what is absent: no maximum layer count, no line width, no impedance tolerance, no HDI stack definition. This company publishes product categories, not process limits. For a 20-layer backplane quote, those limits have to be extracted in writing.
The plant-level numbers, and a thin margin
For the first half of 2026 the Huangshi entity alone reported revenue of RMB 674.09 million and net profit of RMB 36.22 million. That is a 5.4% net margin, on a plant that has been running for five years and is now absorbing conversion capital.
For a buyer this cuts both ways. Thin margins at a plant under retooling are a negotiating position; they are also a reason to watch continuity of supply during the changeover. Ask what fraction of capacity has already been moved to server work, and what happens to a non-server order that is mid-qualification when the line is rebuilt.
Who this plant fits
Server, switch, optical module and storage work, at 12 layers and up, with a supplier whose parent files in two jurisdictions and therefore has audited group numbers. The AI server build-out is a genuine capability signal, not a slogan: UBB and SXM work is hard, and the conversion is being funded.
It does not fit a buyer who needs a stable multi-year automotive line with no process drift, or one who wants a published layer count and impedance tolerance before the first call.
What remains open
No unified social credit code, no registered capital for the Huangshi entity, no plant area or headcount at site level, no monthly capacity, no certificate numbers. The “largest single plant” claim has no first-party confirmation and is contradicted by the company’s own 29,500 m² figure. Which product mix the plant will run in 2028 is stated only as an intention.
Published limits
Every value below is quoted as published by the company or a public record.
| Parameter | Value as published |
|---|---|
| Switch and server boards | Switch boards 12 layers and up; 9:1 aspect ratio; laminate grade one step above server |
| Optical module boards | Mostly HDI; very-low-loss or above, pure or hybrid with FR-4 |
| SSD storage boards | Rigid-flex designs, 3D stacking at package level |
| AI server boards | Switch boards and UBB mainboards; multi-PCIe; direct SXM and OAM accelerator links |
| CPU platform coverage | Intel, AMD and Arm; single, dual and four-socket mainboards |
| Huangshi output, H1 2026 | Revenue RMB 674.09M; net profit RMB 36.22M, sole entity |
| Plant repositioning | Lines being converted and upgraded for server output; targeted as main domestic AI server PCB base |
| Group scale | 4,998 staff; RMB 5.485bn annual revenue; four plants |
| Project investment | RMB 5bn total; groundbreaking April 2020 |
Certifications on record
A certificate covers a legal entity and a site, not a brand. Scope and expiry are recorded where published.
| Standard | What the record shows |
|---|---|
| ISO 9001:2015 | 2025 ESG report scope table covers Guangzhou, Huangshi, Thailand and Dongguan; no certificate number given |
| IATF 16949:2016 | 2025 ESG report lists Guangzhou and Huangshi only, so the automotive system does reach this plant |
| ISO 14001:2015 and ISO 45001:2018 | 2025 ESG report: environmental and safety systems across all four plants including Huangshi |
| QC 080000:2017 | 2025 ESG report: hazardous-substance system covering all four plants, Huangshi included |
| ISO 50001:2018 | 2025 ESG report: energy management at Guangzhou and Huangshi only |
| ISO 27001 | Website still shows the 2013 revision; the ESG report puts the current system at Guangzhou, Huangshi, Dongguan |
Ask this factory for a quote
Send one technical package and compare the replies. The RFQ checklist lists what to include; the quote specifications say which parameters change the price for the process you are buying.
Source and review conventions are described in how we verify. Corrections can be sent through the contact channel.